Yuliivka 74

The turn-key project for restoration of killed well No. 74 of Yuliyevskoe oil and gas condensate field by method of side-tracking from Ø140 mm casing pipe.

PROJECT IMPLEMENTATION STAGES

Window cutting in Ø140 mm casing pipe at the depth of 3,407-3,410 m.

Drilling of an inclined side well shaft in the interval of 3,410-3,622 m with displacement of 210 m from the old shaft.

Well casing with a Ø102 mm shank.

The well drilling was performed using oil emulsion wash fluid.

The well was successfully restored.

Quotations

Twitter

navigator__k В США началась крупнейшая за 35 лет забастовка нефтяников. И Баррель нефти Brent подорожал до 56 долларов. http://t.co/sgKWI0aFpZ
navigator__k "Ой все": JKX Oil & Gas прекращает инвестиции в Украине из-за повышения налогов. http://t.co/cHJoPdwUeT . http://t.co/eY0nRZvKsC

Navigator Komplekt, LLC

The Company provides gas and oil wells drilling, integrated repair of drilling stations, restoration of wells by side-tracking method, drilling projects management.

03680 Kyiv, Palladin Ave, 44

Tel.: +380 (44) 500-85-64

   

JoomShaper
// google analytics